Restructured Energy Market (REM) ISO Rules

Important Dates & Materials

October 22 | Stakeholder Session | REM Implementation and Market Readiness Office Hours registration

October 16 | Window 1 Stakeholder Written Feedback Due

October 6 | Hybrid - REM ISO Rules and ISO Manuals Stakeholder Session (Window 1) presentation

September 21 | Stakeholder Update | Launch of Stakeholder Engagement for REM ISO Rules and ISO Manuals and release of window 1 engagement documents


Engagement Schedule



Sept. 21, 2026 | Stakeholder Update

On September 17, 2026, the AESO hosted a Market Participant Readiness session that included an update on the AESO’s engagement plans for revisions to the REM ISO rules, and ISO manuals.

A summary of the engagement schedule that has been planned for REM ISO rule revisions and ISO manuals can be found above. Any changes to this schedule will be shared here on AESO engage.

On September 21, 2026, the AESO launched its purpose, plan and process for the REM ISO Rules and ISO Manuals Engagement (see below) and posted engagement documents for the following REM ISO rules in window 1:

  • Section 103.17, Access to ISO Systems;
  • Section 210.1, Pool Participant Registration;
  • Section 210.4, Market Messaging and Dispatch Service;
  • Section 210.6, Methods and Coordination of Market Submissions;
  • Section 212.10, 30-Minute Ramping Reserve Qualification and Cost Allocation;
  • Section 213.1, Real-Time Market Offers and Bids;
  • Section 213.2, Real-Time Market Restatements;
  • Section 213.4, 30-Minute Ramping Reserve Demand Curves; and
  • Section 215.1, Dispatches.

The window 1 engagement documents posted include:

  1. Letter of Notice for Stakeholder Engagement on the Restructured Energy Market (“REM”) ISO rules for window 1
  2. Proposed Amended or New REM ISO rules for window 1;
  3. A Summary of Proposed Revisions that summarize amendments to the REM ISO rules in window 1;
  4. Proposed Amended REM ISO rules Consolidated Authoritative Document Glossary addressing terms in window 1; and
  5. Blacklines of REM ISO rules for window 1 against the March 12, 2026 approved version.

Since the REM ISO Rules were approved by the Minister of Affordability and Utilities on March 12, 2026, the AESO has received questions from stakeholders related to the REM ISO rules. The AESO will be posting responses shortly.

Registration for the window 1 stakeholder session on October 6, 2026 is now open. Stakeholder written feedback on the window 1 REM ISO rules is due October 16, 2026. The AESO anticipates providing responses to stakeholder feedback by November 30, 2026.


Purpose – Launch of Stakeholder Engagement for REM ISO Rules and ISO Manuals (September 2026)

The Restructured Energy Market (“REM”) ISO rules required to implement the AESO’s Restructured Energy Market Final Design (“REM Final Design”) were approved by the Minister of Affordability and Utilities on March 12, 2026, through the Restructured Energy Market ISO Rules Regulation. Further information related to the approved REM ISO rules can be found on the REM ISO rules webpage on the AESO website.

Since approval, the AESO has continued to develop the operational and information technology systems required for REM. Revisions to the approved REM ISO rules are required to align with these systems. ISO manuals are in some cases required to set out inputs or processes that must be followed for the REM.

The AESO has established four engagement “windows” to engage with stakeholders from September 2026 to April 2027 on required revisions to the approved REM ISO rules, new REM ISO rules that may be required, and associated ISO manuals. These engagement windows were initially announced during the Market Participant Readiness stakeholder sessions held on March 24, 2026, and again in sessions held on May 13, 2026, and September 17, 2026.


Engagement Plan and Process (September 2026)

With each engagement window the AESO will:

  1. Publish the following materials for stakeholder review:
    • Proposed Amended or New REM ISO rules;
    • where applicable, draft ISO manuals;
    • a Summary of Proposed Revisions that summarizes amendments to content of the REM ISO rule;
    • a Proposed Amended REM ISO rules Consolidated Authoritative Document Glossary; and
    • Blacklines of REM ISO rules against the March 12, 2026 approved version.
  2. Host a stakeholder session to discuss the REM ISO rule and any applicable ISO manuals.
  3. Provide stakeholders with an opportunity to provide in-depth and detailed written feedback on each of the REM ISO rules via a separate survey forum through AESO Engage.
  4. Provide a response to stakeholder feedback.

The proposed engagement schedule for each of the four windows below:


Window Opens / Session Registration Opens
Stakeholder Session
Deadline for Stakeholder Feedback
AESO Response to Stakeholder Feedback
Window 1
September 21, 2026
October 6, 2026
October 16, 2026
November 30, 2026
Window 2
November 6, 2026
November 17, 2026
December 4, 2026
January 29, 2027
Window 3
December 1, 2026
December 10, 2026
January 15, 2027
March 1, 2027
Window 4
February 1, 2027
February 16, 2027
March 1, 2027
April 6, 2027

*Engagement schedule dates are subject to change.

Registration for the window 1 stakeholder session on October 6, 2026 is now open. Registration details related to future stakeholder sessions will be announced on AESO Engage when available. Any changes to this schedule will be shared here on AESO engage.

The AESO is targeting for Ministerial Approval of the proposed amended REM ISO rules and proposed ISO manuals by Q2, 2027.

Important Dates & Materials

October 22 | Stakeholder Session | REM Implementation and Market Readiness Office Hours registration

October 16 | Window 1 Stakeholder Written Feedback Due

October 6 | Hybrid - REM ISO Rules and ISO Manuals Stakeholder Session (Window 1) presentation

September 21 | Stakeholder Update | Launch of Stakeholder Engagement for REM ISO Rules and ISO Manuals and release of window 1 engagement documents


Engagement Schedule



Sept. 21, 2026 | Stakeholder Update

On September 17, 2026, the AESO hosted a Market Participant Readiness session that included an update on the AESO’s engagement plans for revisions to the REM ISO rules, and ISO manuals.

A summary of the engagement schedule that has been planned for REM ISO rule revisions and ISO manuals can be found above. Any changes to this schedule will be shared here on AESO engage.

On September 21, 2026, the AESO launched its purpose, plan and process for the REM ISO Rules and ISO Manuals Engagement (see below) and posted engagement documents for the following REM ISO rules in window 1:

  • Section 103.17, Access to ISO Systems;
  • Section 210.1, Pool Participant Registration;
  • Section 210.4, Market Messaging and Dispatch Service;
  • Section 210.6, Methods and Coordination of Market Submissions;
  • Section 212.10, 30-Minute Ramping Reserve Qualification and Cost Allocation;
  • Section 213.1, Real-Time Market Offers and Bids;
  • Section 213.2, Real-Time Market Restatements;
  • Section 213.4, 30-Minute Ramping Reserve Demand Curves; and
  • Section 215.1, Dispatches.

The window 1 engagement documents posted include:

  1. Letter of Notice for Stakeholder Engagement on the Restructured Energy Market (“REM”) ISO rules for window 1
  2. Proposed Amended or New REM ISO rules for window 1;
  3. A Summary of Proposed Revisions that summarize amendments to the REM ISO rules in window 1;
  4. Proposed Amended REM ISO rules Consolidated Authoritative Document Glossary addressing terms in window 1; and
  5. Blacklines of REM ISO rules for window 1 against the March 12, 2026 approved version.

Since the REM ISO Rules were approved by the Minister of Affordability and Utilities on March 12, 2026, the AESO has received questions from stakeholders related to the REM ISO rules. The AESO will be posting responses shortly.

Registration for the window 1 stakeholder session on October 6, 2026 is now open. Stakeholder written feedback on the window 1 REM ISO rules is due October 16, 2026. The AESO anticipates providing responses to stakeholder feedback by November 30, 2026.


Purpose – Launch of Stakeholder Engagement for REM ISO Rules and ISO Manuals (September 2026)

The Restructured Energy Market (“REM”) ISO rules required to implement the AESO’s Restructured Energy Market Final Design (“REM Final Design”) were approved by the Minister of Affordability and Utilities on March 12, 2026, through the Restructured Energy Market ISO Rules Regulation. Further information related to the approved REM ISO rules can be found on the REM ISO rules webpage on the AESO website.

Since approval, the AESO has continued to develop the operational and information technology systems required for REM. Revisions to the approved REM ISO rules are required to align with these systems. ISO manuals are in some cases required to set out inputs or processes that must be followed for the REM.

The AESO has established four engagement “windows” to engage with stakeholders from September 2026 to April 2027 on required revisions to the approved REM ISO rules, new REM ISO rules that may be required, and associated ISO manuals. These engagement windows were initially announced during the Market Participant Readiness stakeholder sessions held on March 24, 2026, and again in sessions held on May 13, 2026, and September 17, 2026.


Engagement Plan and Process (September 2026)

With each engagement window the AESO will:

  1. Publish the following materials for stakeholder review:
    • Proposed Amended or New REM ISO rules;
    • where applicable, draft ISO manuals;
    • a Summary of Proposed Revisions that summarizes amendments to content of the REM ISO rule;
    • a Proposed Amended REM ISO rules Consolidated Authoritative Document Glossary; and
    • Blacklines of REM ISO rules against the March 12, 2026 approved version.
  2. Host a stakeholder session to discuss the REM ISO rule and any applicable ISO manuals.
  3. Provide stakeholders with an opportunity to provide in-depth and detailed written feedback on each of the REM ISO rules via a separate survey forum through AESO Engage.
  4. Provide a response to stakeholder feedback.

The proposed engagement schedule for each of the four windows below:


Window Opens / Session Registration Opens
Stakeholder Session
Deadline for Stakeholder Feedback
AESO Response to Stakeholder Feedback
Window 1
September 21, 2026
October 6, 2026
October 16, 2026
November 30, 2026
Window 2
November 6, 2026
November 17, 2026
December 4, 2026
January 29, 2027
Window 3
December 1, 2026
December 10, 2026
January 15, 2027
March 1, 2027
Window 4
February 1, 2027
February 16, 2027
March 1, 2027
April 6, 2027

*Engagement schedule dates are subject to change.

Registration for the window 1 stakeholder session on October 6, 2026 is now open. Registration details related to future stakeholder sessions will be announced on AESO Engage when available. Any changes to this schedule will be shared here on AESO engage.

The AESO is targeting for Ministerial Approval of the proposed amended REM ISO rules and proposed ISO manuals by Q2, 2027.

  • Instructions for Written Feedback

    What we need from Stakeholders:

    • Feedback that is authorized by an organization
    • Solution oriented written feedback on why and how specific REM ISO rule provisions should be changed  

    In Scope:

    • Feedback on whether the REM ISO rules align with the final REM design
    • Feedback on whether the REM ISO rules are technically sufficient:
      • Clear and concise
      • Complete (to the extent possible)
      • Practically implementable
      • Consistent with the statutory scheme, including the Electric Utilities Act (as amended by Bill 52)

    Out of Scope:

    • Revisiting the final REM Design


    While providing written feedback:

    • One response per organization.
    • All submissions will be published on AESO Engage, in its original state.
    • Responses due on or before 4:00 p.m. MDT on October 16, 2026.


    Note: We recommend that responses are prepared in a word document (or some other document processing system) and when ready to submit, the answers are copied and pasted for each question back into the survey response comment box. The formatting (numbering/bullets) may not appear as drafted in the survey comment response; however, the formatting is retained when the responses are exported by the AESO. 

    Submit Feedback
  • CLOSED: This feedback opportunity has concluded.

    We value stakeholder input and invite stakeholders to provide their feedback on the materials presented on June 15 for Market Power Mitigation for Energy Storage/Hydro Assets via the following stakeholder feedback form by July 15, at 4:00 p.m. MT. Please be as specific as possible with your responses. Thank you for your input.

    Purpose

    Following our session on June 15, 2026, we are inviting written comments from stakeholders that will inform ISO manual content on reference levels and the secondary offer cap, and possible related REM ISO rule changes.

    Instructions

    1. This feedback form is open to all industry stakeholders.
    2. Please fill out the sections below as indicated.
    3. Only one completed feedback form will be accepted per organization.
    4. To upload your completed feedback form:

    • You will need to be registered and signed in on the AESO Engage platform; and
    • You will need to be on the REM ISO Rules page, which can be found on the AESO website at www.aeso.ca and follow the path: AESO Engage (found on very top navigation bar) > Hub > ISO Rules; and Restructured Energy Market (REM) ISO Rules

    5. Click on the "Submit Stakeholder Feedback" box below to upload your completed feedback form.

    All responses are due by July 15, 2026, at 4:00 p.m. MT. and will be shared on AESO Engage in their original format. If you have any questions, please email stakeholder.relations@aeso.ca

    Questions

    Broad Market Power Mitigation for Energy Storage/Hydro Resources

    1. Share comments or feedback on the framework presented. 

    Local Market Power Mitigation for Energy Storage/Hydro Resources

    2. Share comments or feedback on the framework presented.

  • CLOSED: This feedback opportunity has concluded.

    We value stakeholder input and invite stakeholders to provide their feedback on the materials presented on June 15 for the proposed CONE Study via the following stakeholder feedback form by July 15, at 4:00 p.m. MT. Please be as specific as possible with your responses. Thank you for your input.

    Purpose

    Following our session on June 15, 2026, we are inviting written comments from stakeholders that will help us refine the scope of the Cost of New Entry Study.

    Instructions

    1. This feedback form is open to all industry stakeholders.
    2. Please fill out the sections using the written feedback form provided. 
    3. Only one completed feedback form will be accepted per organization.
    4. To upload your completed feedback form:

    • You will need to be registered and signed in on the AESO Engage platform; and
    • You will need to be on the REM ISO Rules page, which can be found on the AESO website at www.aeso.ca and follow the path: AESO Engage (found on very top navigation bar) > Hub > ISO Rules; and Restructured Energy Market (REM) ISO Rules

    5. Click on the "Submit Stakeholder Feedback" box below to upload your completed feedback form.

    All responses are due by July 15, 2026, at 4:00 p.m. MT. and will be shared on AESO Engage in their original format. If you have any questions, please email stakeholder.relations@aeso.ca

    Questions

    1. Are there additional generation technologies that should be included in the study? 

    2. What criteria should be used to select a reference technology for the Secondary Offer Cap (SOC)?

    3. Do you have feedback on using combined cycle natural gas as the SOC reference technology?

    4. If combined cycle natural gas is not appropriate as the SOC reference technology, what alternative would you suggest, and why?

    5. What indices should be used to track reference technology costs over the 5-year CONE study period?

    6. Do you have any other feedback on the proposed CONE Study process?

  • CLOSED: This survey has concluded.

    Purpose

    We have published a summary of the Opportunity Cost Methodology for Market Power Mitigation stakeholder session on November 6, 2025. We invite interested stakeholders to review and provide additional comments by December 15, 2025. 

    Instructions

    • To submit your responses, you will need to be registered and signed in on the AESO Engage platform. 
    • Please click on the "Submit Feedback " box below to begin the survey and provide your specific comments. 
    • Please submit one completed survey per organization. 
    • All responses will be shared on AESO Engage. 
    • Responses are due by December 15, 2025.

    Questions

    1. Out of the options presented, which option are you most aligned with and why?
    2. What modifications would you propose to improve the options presented?
    3. If you think an alternative option for mitigating Energy Storage Resources (ESR) and Hydro should be pursued, can you please describe it in detail below including how it would be calculated, and how you think it would address the market power concerns of these types of resources?
    4. Are there any other considerations that the AESO should be mindful of when determining an opportunity cost level for ESR and Hydro?
  • CLOSED: This survey has concluded.

    Purpose

    Following a stakeholder session the AESO hosted on November 5, 2025, stakeholder feedback received October 20, 2025, and discussions during the October 9, 2025 technical session, the AESO has posted the Dispatch Compliance and Allowable Dispatch Variance design. We invite interested stakeholders to provide comments by December 1, 2025. 

    Instructions

    • To submit your responses, you will need to be registered and signed in on the AESO Engage platform. 
    • Please click on the "Submit Feedback " box below to begin the survey and provide your specific comments. 
    • Please submit one completed survey per organization. 
    • All responses will be shared on AESO Engage. 
    • Responses are due by December 1, 2025.

    Questions

    1. Please provide your feedback related to the REM ISO Rules: Dispatch Compliance and Allowable Dispatch Variance
  • CLOSED: This survey has concluded.

    Purpose

    In response to stakeholder feedback received on the proposed REM ISO rules following their release on September 4, 2025, the AESO has published an update to Stakeholders on the AESO’s approach to methodological content. We invite interested Stakeholders to provide comments by December 1, 2025. 

     

    Instructions

    1. To submit comments, you will need to have registered and be signed-in on the AESO Engage platform.
    2. Please click on the "Submit Feedback Here" box below to begin the survey and provide your specific comments.
    3. Please submit one completed survey per organization.
    4. All responses will be shared on AESO Engage.
    5. Responses are due by December 1, 2025.


  • CLOSED: This survey has concluded.

    Instructions for Written Feedback

    What we need from Stakeholders:

    • Feedback that is authorized by an organization
    • Solution oriented written feedback on why and how specific REM ISO rule provisions should be changed  

    In Scope:

    • Feedback on whether the REM ISO rules align with the final REM design
    • Feedback on whether the REM ISO rules are technically sufficient:
      • Clear and concise
      • Complete (to the extent possible)
      • Practically implementable
      • Consistent with the statutory scheme, including the Electric Utilities Act (as amended by Bill 52)

    Out of Scope:

    • Revisiting the final REM Design


    While providing written feedback:

    • One response per organization.
    • All submissions will be published on AESO Engage, in its original state.
    • Responses due on or before 4:00 p.m. MDT on October 20, 2025.


    Note: We recommend that responses are prepared in a word document (or some other document processing system) and when ready to submit, the answers are copied and pasted for each question back into the survey response comment box. The formatting (numbering/bullets) may not appear as drafted in the survey comment response; however, the formatting is retained when the responses are exported by the AESO. 

Page last updated: 07 Oct 2026, 04:07 PM