To make required changes to the Tariff to align with the current AESO Connection Process, provide clarity where needed and enable a more efficient process. We will not be making significant changes to the AESO Connection Process as part of this engagement.
To make required changes to the Tariff to align with the current AESO Connection Process, provide clarity where needed and enable a more efficient process. We will not be making significant changes to the AESO Connection Process as part of this engagement.
To validate our summary of opportunities to improve the ISO tariff is comprehensive and nothing is missing or out of line with what stakeholders are experiencing. All stakeholder feedback we receive will be shared as received, and we will publish a directional summary after all feedback has been reviewed. If any topics require more detailed information, discussion or context, additional phases of consultation may be added.
Amendments for the AESO Connection Process is currently at this stage
Presentation providing context is available under AESO Materials. Deadline for feedback is May 27, 2025.
May - August, 2025
this is an upcoming stage for Amendments for the AESO Connection Process
The AESO will review stakeholder feedback received and prepare blacklines of the relevant ISO tariff Terms and Conditions, as well as a directional summary.
August - October, 2025
this is an upcoming stage for Amendments for the AESO Connection Process
Summary of feedback and blacklines posted. Deadline for feedback on blacklines is October 2025.
If any topics require more detailed information, discussion or context, additional phases of consultation may be added prior to finalizing the Tariff Terms and Conditions.
AUC Process | Q4, 2025 - Q1, 2026
this is an upcoming stage for Amendments for the AESO Connection Process
The AESO draft and file its ISO tariff Terms and Conditions application with the Alberta Utilities Commission (AUC)