Amendments for the AESO Connection Process

Important Dates & Materials

May 6 | Combined TRP & Amendments for the Connection Process stakeholder feedback posted

Stakeholder Update | June 29, 2026

Due to complex interdependencies discovered through engagement and taking into consideration stakeholder feedback, the engagement schedule has been adjusted as follows. Note: These dates are tentative and being shared for stakeholder planning purposes.

Expected DateActivity
end of July 2026AESO to post Tariff Terms & Conditions (Ts&Cs) blacklines for stakeholder review
mid-end August 2026Stakeholder feedback on blacklines due
September 2026Filing of AUC application



Engagement Schedule (updated Jun. 29, 2026)



Purpose

To make required changes to the Tariff to align with the current AESO Connection Process, provide clarity where needed and enable a more efficient process. We will not be making significant changes to the AESO Connection Process as part of this engagement.

This engagement process will review the following ISO tariff components:

  • System Access Service (SAS) Agreements for Rate DTS and Rate STS
  • Construction Commitment Agreements (CCA) and Security paid to the TFOs
  • Payment in Lieu of Notice (PILON)
  • Overall layout and presentation of content in Sections 3, 5, and 6 of the ISO tariff

Throughout 2022 to 2024, we streamlined the Connection Process by developing the Cluster Assessment Process with robust stakeholder input.


Out of Scope

Although there will be overlap and interdependencies, the below topics/workstreams are out-of-scope and will be covered in other work streams:

  • Existing GUOC provisions, as well as design of the new Transmission Reinforcement Payment (TRP)
  • Ancillary Services cost allocation
  • Transmission cost allocation and contribution policy
  • Internal demand rates

Important Dates & Materials

May 6 | Combined TRP & Amendments for the Connection Process stakeholder feedback posted

Stakeholder Update | June 29, 2026

Due to complex interdependencies discovered through engagement and taking into consideration stakeholder feedback, the engagement schedule has been adjusted as follows. Note: These dates are tentative and being shared for stakeholder planning purposes.

Expected DateActivity
end of July 2026AESO to post Tariff Terms & Conditions (Ts&Cs) blacklines for stakeholder review
mid-end August 2026Stakeholder feedback on blacklines due
September 2026Filing of AUC application



Engagement Schedule (updated Jun. 29, 2026)



Purpose

To make required changes to the Tariff to align with the current AESO Connection Process, provide clarity where needed and enable a more efficient process. We will not be making significant changes to the AESO Connection Process as part of this engagement.

This engagement process will review the following ISO tariff components:

  • System Access Service (SAS) Agreements for Rate DTS and Rate STS
  • Construction Commitment Agreements (CCA) and Security paid to the TFOs
  • Payment in Lieu of Notice (PILON)
  • Overall layout and presentation of content in Sections 3, 5, and 6 of the ISO tariff

Throughout 2022 to 2024, we streamlined the Connection Process by developing the Cluster Assessment Process with robust stakeholder input.


Out of Scope

Although there will be overlap and interdependencies, the below topics/workstreams are out-of-scope and will be covered in other work streams:

  • Existing GUOC provisions, as well as design of the new Transmission Reinforcement Payment (TRP)
  • Ancillary Services cost allocation
  • Transmission cost allocation and contribution policy
  • Internal demand rates
  • Stakeholder Updates

    Stakeholder Update | June 29, 2026

    Due to complex interdependencies discovered through engagement and taking into consideration stakeholder feedback, the engagement schedule has been adjusted as follows. Note: These dates are tentative and being shared for stakeholder planning purposes.

    Expected DateActivity
    end of July 2026AESO to post Tariff Terms & Conditions (Ts&Cs) blacklines for stakeholder review
    mid-end August 2026Stakeholder feedback on blacklines due
    September 2026Filing of AUC application

    Date Adjustment for the October Workshop | Oct. 8, 2025

    With the Oct. 21-22 Ancillary Services Cost Allocation workshop being postponed, we will now host the Transmission Reinforcement Payment (TRP) & Amendments for the Connection Process Workshop on Oct. 22-23.

    You have until Tuesday, Oct. 14 to submit or adjust your request to attend in-person(External link), and will receive a confirmation of your attendance afterwards.

    Directional Summary Update | June 16, 2025

    The AESO appreciates and thanks stakeholders for their fulsome insights on proposed Tariff amendments for the AESO Connection Process. We are now taking time to review all feedback and will be publishing the directional summary, along with proposed blacklines by the end of August 2025.

    Stakeholder Update | June 29, 2026

    Due to complex interdependencies discovered through engagement and taking into consideration stakeholder feedback, the engagement schedule has been adjusted as follows. Note: These dates are tentative and being shared for stakeholder planning purposes.

    Expected DateActivity
    end of July 2026AESO to post Tariff Terms & Conditions (Ts&Cs) blacklines for stakeholder review
    mid-end August 2026Stakeholder feedback on blacklines due
    September 2026Filing of AUC application

    Date Adjustment for the October Workshop | Oct. 8, 2025

    With the Oct. 21-22 Ancillary Services Cost Allocation workshop being postponed, we will now host the Transmission Reinforcement Payment (TRP) & Amendments for the Connection Process Workshop on Oct. 22-23.

    You have until Tuesday, Oct. 14 to submit or adjust your request to attend in-person(External link), and will receive a confirmation of your attendance afterwards.

    Directional Summary Update | June 16, 2025

    The AESO appreciates and thanks stakeholders for their fulsome insights on proposed Tariff amendments for the AESO Connection Process. We are now taking time to review all feedback and will be publishing the directional summary, along with proposed blacklines by the end of August 2025.

Page last updated: 29 Jun 2026, 12:10 PM