Purpose
The AESO is embarking on a pivotal initiative to adopt the latest TPL and SOL Standards, as part of its ongoing commitment to enhance the reliability of the transmission system in Alberta. These standards introduce critical requirements that will govern transmission planning assessments in Alberta.
Background
The facilities design, connections, and maintenance standards play a crucial role in ensuring the reliable planning and operation of the bulk electric system by establishing and communicating system operating limits. This initiative aims to enhance these standards by refining the process for determining and communicating system operating limits. The proposed revisions to standards and definitions will streamline requirements, ensuring they align seamlessly with transmission planning standards, while maintaining consistency with transmission operations and interconnection reliability operations standards. The updates will also address challenges in accurately determining and communicating system operating limits and interconnection reliability operating limits.
In particular, the proposed new PRC-026-AB-2 will create a standard for relay performance during stable power swings that provides criteria for inclusion and evaluation of system elements. Proposed changes to the TPL standards will update the contingencies used in transmission planning and provide steady state and stability performance requirements for events planning and extreme events. Proposed changes in the updated IRO-008-AB-3 standard include the introduction of notification requirements for impacted operators, where real-time assessment indicates that the system operating limits are exceeded. The FAC-003, FAC-011, and FAC-014 standards are also being revised to update their applicability, better align with NERC, and clarify and simplify the requirements.
Key Dates
June 6, 2025 | Stakeholder Feedback on TOP Standard and ID#2025-002 due
May 30, 2025 | Stakeholder Feedback on Proposed TPL and SOL Standards due
May 27, 2025 | Extension of Comment Deadline - TOP Standard Letter posted
May 16, 2025 | AESO Reply and Consultation Letter and supporting material posted
Purpose
The AESO is embarking on a pivotal initiative to adopt the latest TPL and SOL Standards, as part of its ongoing commitment to enhance the reliability of the transmission system in Alberta. These standards introduce critical requirements that will govern transmission planning assessments in Alberta.
Background
The facilities design, connections, and maintenance standards play a crucial role in ensuring the reliable planning and operation of the bulk electric system by establishing and communicating system operating limits. This initiative aims to enhance these standards by refining the process for determining and communicating system operating limits. The proposed revisions to standards and definitions will streamline requirements, ensuring they align seamlessly with transmission planning standards, while maintaining consistency with transmission operations and interconnection reliability operations standards. The updates will also address challenges in accurately determining and communicating system operating limits and interconnection reliability operating limits.
In particular, the proposed new PRC-026-AB-2 will create a standard for relay performance during stable power swings that provides criteria for inclusion and evaluation of system elements. Proposed changes to the TPL standards will update the contingencies used in transmission planning and provide steady state and stability performance requirements for events planning and extreme events. Proposed changes in the updated IRO-008-AB-3 standard include the introduction of notification requirements for impacted operators, where real-time assessment indicates that the system operating limits are exceeded. The FAC-003, FAC-011, and FAC-014 standards are also being revised to update their applicability, better align with NERC, and clarify and simplify the requirements.
-
Reliability Standards Workshop | December 10, 2024
CLOSED: This discussion has concluded.Purpose
The purpose of the session is to engage stakeholders in an active discussion on the TPL and SOL Standards as described in the Consultation Letter posted on AESO Engage September 27, 2024. The session objectives are as follows:
- Address Stakeholder questions and concerns received on or before November 15, 2024, related to the TPL-SOL ARS Project consultation material posted September 27, 2024.
- Discuss Reliability Standard Audit Worksheets (RSAWs).
- Kick off detailed discussions to facilitate the finalizing of TPL-001-AB-5.1 and related ID and its implementation.
Session Details
Date: Tuesday, December 10, 2024
Time: 9:30 a.m. to 4:00 p.m.
Virtual option: Teams webinar
Registration: You must pre-register to participate and can do so by clicking the secure link here.
For more details view the Reliability Standards Workshop Invitation.
Reliability Standards Workshop materials
Can be found in the AESO Materials section.
Signup Banner
Level of Engagement
Consult: Gather input and feedback from stakeholders
Refer to the AESO’s Engagement Framework for our approach to engagement
Stakeholder Submissions
AESO Materials for Stakeholder Feedback | May 16 - June 6, 2025
AESO Materials for Stakeholder Feedback | May 16 - May 30, 2025
-
AESO Reply and Consultation Letter (Posted May 16 2025) (665 KB) (pdf)
-
Stakeholder Comment and AESO Replies Matrix - Sept 27 2024 to Nov 15 2024 (Posted May 16 2025) (1.24 MB) (pdf)
-
Stakeholder Comment and AESO Replies Matrix - Jan 14 2025 and Feb 4 2025 (Posted May 16 2025) (817 KB) (pdf)
-
Clean - Rationale for Proposed ARS Deviations (Posted May 16 2025) (526 KB) (pdf)
-
Blackline - Rationale for Proposed ARS Deviations - 2024-09-27 and Rationale for Proposed ARS Deviations - 2025-05-16 (Posted May 16 2025) (526 KB) (pdf)
-
Clean - Concordance Document (Posted May 16 2025) (421 KB) (pdf)
-
Blackline - Concordance Document - 2024-09-27 and Concordance Document - 2025-05-16 (Posted May 16 2025) (373 KB) (pdf)
-
TPL and SOL Standards
-
Clean - FAC-003-AB-5 (Posted May 16 2025) (422 KB) (pdf)
-
Blackline - FAC-003-AB-5 - 2024-09-27 and FAC-003-AB-5 - 2025-05-16 (Posted May 16 2025) (508 KB) (pdf)
-
Blackline - NERC FAC-003-5 and FAC-003-AB-5 - 2025-05-16 (Posted May 16 2025) (639 KB) (pdf)
-
Blackline - FAC-003-AB1-1 and FAC-003-AB-5 - 2025-05-16 (Posted May 16 2025) (479 KB) (pdf)
-
Clean - FAC-011-AB-4 (Posted May 16 2025) (188 KB) (pdf)
-
Blackline - FAC-011-AB-4 - 2024-09-27 and FAC-011-AB-4 - 2025-05-16 (Posted May 16 2025) (181 KB) (pdf)
-
Blackline - NERC FAC-011-AB-4 and FAC-011-AB-4 - 2025-05-16 (Posted May 16 2025) (227 KB) (pdf)
-
Blackline - FAC-011-AB-2 and FAC-011-AB-4 - 2025-05-16 (Posted May 16 2025) (207 KB) (pdf)
-
Clean - FAC-014-AB-3 (Posted May 16 2025) (145 KB) (pdf)
-
Blackline - FAC-014-AB-3 - 2024-09-27 and FAC-014-AB-3 - 2025-05-16 (Posted May 16 2025) (95.9 KB) (pdf)
-
Blackline - NERC FAC-014-3 and FAC-014-AB-3 - 2025-05-16 (Posted May 16 2025) (158 KB) (pdf)
-
Blackline - FAC-014-AB1-2 and FAC-014-AB-3 - 2025-05-16 (Posted May 16 2025) (137 KB) (pdf)
-
Clean - IRO-008-AB-3 (Posted May 16 2025) (123 KB) (pdf)
-
Blackline - IRO-008-AB-3 - 2024-09-27 and IRO-008-AB-3 - 2025-05-16 (Posted May 16 2025) (118 KB) (pdf)
-
Blackline - NERC IRO-008-AB-3 and IRO-008-AB-3 - 2025-05-16 (Posted May 16 2025) (231 KB) (pdf)
-
Blackline - IRO-008-AB-2 and IRO-008-AB-3 - 2025-05-16 (Posted May 16 2025) (128 KB) (pdf)
-
Clean - PRC-002-AB-4 (Posted May 16 2025) (259 KB) (pdf)
-
Blackline - PRC-002-AB-4 - 2024-09-27 and PRC-002-AB-4 - 2025-05-16 (Posted May 16 2025) (251 KB) (pdf)
-
Blackline - NERC PRC-002-4 and PRC-002-AB-4 - 2025-05-16 (Posted May 16 2025) (367 KB) (pdf)
-
Blackline - PRC-002-AB-2 and PRC-002-AB-4 - 2025-05-16 (Posted May 16 2025) (292 KB) (pdf)
-
Clean - PRC-023-AB-6 (Posted May 16 2025) (181 KB) (pdf)
-
Blackline - PRC-023-AB-6 - 2024-09-27 and PRC-023-AB-6 - 2025-05-16 (Posted May 16 2025) (178 KB) (pdf)
-
Blackline - NERC PRC-023-AB-6 and PRC-023-AB-6 - 2025-05-16 (Posted May 16 2025) (247 KB) (pdf)
-
Blackline - PRC-023-AB-4 and PRC-023-AB-6 - 2025-05-16 (Posted May 16 2025) (264 KB) (pdf)
-
Clean - PRC-026-AB-2 (Posted May 16 2025) (4.5 MB) (pdf)
-
Blackline - PRC-026-AB-2 - 2024-09-27 and PRC-026-AB-2 - 2025-05-16 (Posted May 16 2025) (6.02 MB) (pdf)
-
Blackline - NERC PRC-026-AB-2 and PRC-026-AB-2 - 2025-05-16 (Posted May 16 2025) (6.09 MB) (pdf)
-
Clean - TPL-001-AB-5.1 (Posted May 16 2025) (265 KB) (pdf)
-
Blackline - TPL-001-AB-5.1 - 2024-09-27 and TPL-001-AB-5.1 - 2025-05-16 (Posted May 16 2025) (265 KB) (pdf)
-
Blackline - NERC TPL-001-5.1 and TPL-001-AB-5.1 - 2025-05-16 (Posted May 16 2025) (480 KB) (pdf)
-
Clean - Summary of changes in TPL-001-AB-5.1 (Posted May 16 2025) (120 KB) (pdf)
-
Blackline - Notable changes in TPL-001-AB-5.1 - 2024-09-27 and Summary of changes in TPL-001-AB-5.1 - 2025-05-16 (Posted May 16 2025) (131 KB) (pdf)
-
Clean - TPL-001-PLAN-AB-1 (Posted May 16 2025) (231 KB) (pdf)
-
Blackline - TPL-001-PLAN-AB-1 - 2024-09-27 and TPL-001-PLAN-AB-1 - 2025-05-16 (Posted May 16 2025) (346 KB) (pdf)
-
-
AESO IDs
-
Clean - 2012-004RS (Posted May 16 2025) (381 KB) (pdf)
-
Blackline - 2012-004RS - 2024-09-27 and 2012-004RS - 2025-05-16 (Posted May 16 2025) (568 KB) (pdf)
-
Blackline - 2012-004RS - 2018-12-06 and 2012-004RS - 2025-05-16 (Posted May 16 2025) (851 KB) (pdf)
-
Clean - 2018-022 (Posted May 16 2025) (140 KB) (pdf)
-
Blackline - 2018-022 - 2024-09-27 and 2018-022 - 2025-05-16 (Posted May 16 2025) (141 KB) (pdf)
-
Blackline - 2018-022 - 2024-04-01 and 2018-022 - 2025-05-16 (Posted May 16 2025) (152 KB) (pdf)
-
Clean - 2019-002 (Posted May 16 2025) (118 KB) (pdf)
-
Blackline - 2019-002 - 2024-09-27 and 2019-002 - 2025-05-16 (Posted May 16 2025) (118 KB) (pdf)
-
Blackline - 2019-002 - 2022-12-20 and 2019-002 - 2025-05-16 (Posted May 16 2025) (125 KB) (pdf)
-
Clean - 2024-006 (Posted May 16 2025) (141 KB) (pdf)
-
Blackline - 2024-006 - 2024-09-27 and 2024-006 - 2025-05-16 (Posted May 16 2025) (141 KB) (pdf)
-
Clean - 2024-007 (Posted May 16 2025) (172 KB) (pdf)
-
Blackline - 2024-007 - 2024-09-27 and 2024-007 - 2025-05-16 (Posted May 16 2025) (171 KB) (pdf)
-
-
RSAWs
AESO Materials for RSW | December 10, 2024
-
Reliability Standards Workshop Discussion Summary [Posted: 2025-01-14] (378 KB) (pdf)
-
Reliability Standards Workshop Agenda [Posted: 2024-12-03] (546 KB) (pdf)
-
Reliability Standards Workshop Presentation [Posted: 2024-12-03] (1.75 MB) (pdf)
-
Reliability Standards Workshop Invitation [Posted: 2024-11-19] (314 KB) (pdf)
AESO Materials for Stakeholder Feedback | Sept. 27 - Nov. 15, 2024
-
Extension of Comment Deadline - TPL and SOL Standards [Posted: 2024-11-05] (303 KB) (pdf)
-
Consultation Letter [Posted: 2024-09-27] (201 KB) (pdf)
-
TPL-SOL Standards Project Concordance Document [Posted: 2024-09-27] (441 KB) (pdf)
-
Rationale for Proposed TPL-SOL Project Deviations from NERC Reliability Standards [Posted: 2024-09-27] (259 KB) (pdf)
-
TPL and SOL Standards
-
FAC-003-AB-5 Clean [Posted: 2024-09-27] (488 KB) (pdf)
-
Blackline NERC FAC-003-5 to FAC-003-AB-5 [Posted: 2024-09-27] (511 KB) (pdf)
-
Blackline FAC-003-AB-1.1 to FAC-003-5 [Posted: 2024-09-27] (645 KB) (pdf)
-
FAC-011-AB-4 Clean [Posted: 2024-09-27] (210 KB) (pdf)
-
Blackline NERC FAC-011-4 to FAC-011-AB-4 [Posted: 2024-09-27] (259 KB) (pdf)
-
Blackline FAC-011-AB-2 to FAC-011-AB-4 [Posted: 2024-09-27] (216 KB) (pdf)
-
FAC-014-AB-3 Clean [Posted: 2024-09-27] (145 KB) (pdf)
-
Blackline NERC FAC-014-3 to FAC-014-AB-3 [Posted: 2024-09-27] (190 KB) (pdf)
-
Blackline FAC-014-AB1-2 to FAC-014-AB-3 [Posted: 2024-09-27] (128 KB) (pdf)
-
IRO-008-AB-3 Clean [Posted: 2024-09-27] (186 KB) (pdf)
-
Blackline NERC IRO-008-3 to IRO-008-AB-3 [Posted: 2024-09-27] (277 KB) (pdf)
-
Blackline IRO-008-AB-2 to IRO-008-AB-3 [Posted: 2024-09-27] (135 KB) (pdf)
-
PRC-002-AB-4 Clean [Posted: 2024-09-27] (257 KB) (pdf)
-
Blackline NERC PRC-002-4 to PRC-002-AB-4 [Posted: 2024-09-27] (400 KB) (pdf)
-
Blackline PRC-002-AB-2 to PRC-002-AB-4 [Posted: 2024-09-27] (286 KB) (pdf)
-
PRC-023-AB-6 Clean [Posted: 2024-09-27] (235 KB) (pdf)
-
Blackline NERC PRC-023-6 to PRC-023-AB-6 [Posted: 2024-09-27] (336 KB) (pdf)
-
Blackline PRC-023-AB-4 to PRC-023-AB-6 [Posted: 2024-09-27] (277 KB) (pdf)
-
PRC-026-AB-2 Clean [Posted: 2024-09-27] (1.61 MB) (pdf)
-
Blackline NERC PRC-026-2 to PRC-026-AB-2 Posted 2024-09-27 (1.7 MB) (pdf)
-
TPL-001-AB-5.1 Clean [Posted: 2024-09-27] (284 KB) (pdf)
-
Blackline NERC TPL-001-5.1 to TPL-001-AB-5.1 [Posted: 2024-09-27] (972 KB) (pdf)
-
Notable changes in TPL-001-AB-5.1 [Posted: 2024-09-27] (137 KB) (pdf)
-
TPL-001-PLAN-AB-1 Clean [Posted: 2024-09-27] (300 KB) (pdf)
-
-
AESO IDs
-
ID 2012-004RS Clean [Posted: 2024-09-27] (438 KB) (pdf)
-
ID 2012-004RS Blackline [Posted: 2024-09-27] (713 KB) (pdf)
-
ID 2018-022 Clean [Posted: 2024-09-27] (191 KB) (pdf)
-
ID 2018-022 Blackline [Posted: 2024-09-27] (156 KB) (pdf)
-
ID 2019-002 Clean [Posted: 2024-09-27] (169 KB) (pdf)
-
ID 2019-002 Blackline [Posted: 2024-09-27] (145 KB) (pdf)
-
ID 2024-006 Clean [Posted: 2024-09-27] (149 KB) (pdf)
-
ID 2024-007 Clean [Posted: 2024-09-27] (176 KB) (pdf)
-
-
RSAWs
Historical Key Dates
-
November → December 2024
Lifecycle
-
Stakeholder Feedback | Sept. 27, 2024 - Nov. 15, 2024
TPL and SOL Standards has finished this stageGather written feedback from stakeholders on proposed TPL and SOL Standards.
-
Reliability Standards Workshop | December 10, 2024
TPL and SOL Standards has finished this stageStakeholder Reliability Standards Workshop focused on addressing initial Stakeholder written feedback.
-
Additional Stakeholder Feedback | Jan. 14, 2025 - Feb. 4, 2025
TPL and SOL Standards has finished this stageGather additional written feedback from stakeholders on proposed TPL and SOL Standards.
-
Formal Consultation Material | Mid-May 2025
TPL and SOL Standards has finished this stageThe AESO will post formal consultation materials and responses to all stakeholder feedback received to date on proposed TPL and SOL Standards.
-
Final Stakeholder Feedback | Mid-May to end of May 2025
TPL and SOL Standards is currently at this stageGather final stakeholder written comments on proposed TPL and SOL Standards.
-
Replies to Stakeholders | Mid-June 2025
this is an upcoming stage for TPL and SOL StandardsThe AESO will post replies to final stakeholder written comments.
-
Forward to Commission | end of June 2025
this is an upcoming stage for TPL and SOL StandardsForward final TPL and SOL standards to the Commission.
Contact Us
If you have any other questions, please contact ars_comments@aeso.ca.