Pre-Engagement - Phase II: Large Load Integration
Important Dates & Materials
- November 13 | Deadline to submit application for Phase 2A Working Group
- November 5 | Phase 2A Working Group Launch
- October 21 | Consolidated Survey Responses posted
- October 15 | Pre-engagement survey deadline
- September 26 | Data Centre Update posted
November 5, 2025 | Stakeholder Update
The AESO is launching the Large Load Working Group (“LLWG-2A”), a targeted industry engagement to explore and develop Phase 2A solutions for “bring your own generation” (BYOG) and MW allocations.
The LLWG-2A will collaborate with the AESO to develop a proposal to update the connection process, ensuring it recognizes and accommodates large loads that: (i) self-supply their own power on-site; (ii) enable net new generation on the transmission system; or (ii) require MW allocations. This effort aims to improve transparency and speed-to-market for projects that support Alberta’s reliability and competitiveness.
The LLWG-2A will follow a structured approach to develop the proposal:
- Identify key challenges in the current connection process
- Understand best practices and regulatory considerations
- Contribute to the design and validation of a proposal for BYOG and MW allocations
- Deliver a final proposal for broader industry consultation in 2026
To ensure informed and balanced input, we are targeting representation from the following groups:
- Data centre developers/end use customers (4 - 6 members)
- Generators (1 - 3 members)
- Industrial load customers (1 - 3 members)
LLWG-2A Selection
- Application Deadline: November 13, 2025
- Notification to Selected Members: November 20, 2025
Proposal Development
- Preliminary Kick-off Meeting (virtual): November 27, 2025
- 1:1 meetings with AESO: Week of December 1 and December 8
- Joint LLWG-2A meetings: as needed
Broader Industry Engagement
- Proposal Release, Engagement Sessions, and Written Comment Period: January-February 2026 (ETA)
For additional information, review the Phase 2A Working Group Supplemental Information and Terms of Reference. All interested stakeholders can apply to participate in the working group via the survey below.
Purpose
The AESO rolled out Phase I of the Large Load Integration Program on June 4, 2025. Phase I included a 1,200 MW interim large load connection limit and a process for allocating that load among qualified project developers.
Phase II of the Large Load Integration Program will explore the changes necessary to create the long-term framework for large loads (including data centres) across the AESO’s mandate, including connections, planning, operations, markets, tariff and reliability.
The design of Phase II engagement is still in development and requires careful planning and coordination. To help shape its scope and direction, we are seeking stakeholder input on:
- key questions and related topics to address; and
- structure and timing, considering the interdependencies with other engagements.
See pages 3 and 4 of the latest Data Centre Update for the relevant information to complete the survey below.