Phase 2A: Large Load Integration | BYOG Process
Important Dates & Materials
July 15 | Consolidated Written Feedback posted
July 13 | Deadline for Written Feedback
July 6 | Working Group Feedback posted
June 26 | Materials posted
June 24 | Stakeholder Session presentation and recording
Purpose
The AESO rolled out Phase I of the Large Load Integration Program on June 4, 2025. Phase I included a 1,200 MW interim large load connection limit and a process for allocating that load among qualified project developers.
Phase II of the Large Load Integration Program is exploring the changes necessary to create the long-term framework for large loads (including data centres) across the AESO’s mandate, including connections, planning, operations, markets, tariff and reliability.
We continue to evolve the design of Phase II engagement, which requires careful planning and coordination. To help shape its scope and direction, we sought stakeholder input on:
- key questions and related topics to address; and
- structure and timing, considering the interdependencies with other engagements.
Important Dates & Materials
July 15 | Consolidated Written Feedback posted
July 13 | Deadline for Written Feedback
July 6 | Working Group Feedback posted
June 26 | Materials posted
June 24 | Stakeholder Session presentation and recording
Purpose
The AESO rolled out Phase I of the Large Load Integration Program on June 4, 2025. Phase I included a 1,200 MW interim large load connection limit and a process for allocating that load among qualified project developers.
Phase II of the Large Load Integration Program is exploring the changes necessary to create the long-term framework for large loads (including data centres) across the AESO’s mandate, including connections, planning, operations, markets, tariff and reliability.
We continue to evolve the design of Phase II engagement, which requires careful planning and coordination. To help shape its scope and direction, we sought stakeholder input on:
- key questions and related topics to address; and
- structure and timing, considering the interdependencies with other engagements.
-
Stakeholder Updates
April 21, 2026
The working group was provided with a draft of the front end of the process, including details on load applicability, generator qualification, application submission requirements, tethering agreements, and related terms and conditions. This draft reflected the working group’s discussions to date and was used as the basis for additional meetings held April 13–14 to further refine the approach. The AESO is now incorporating those updates into a revised process draft, which will be published shortly.
For transparency, the draft process shared with the working group is included with this update to provide visibility into the current direction of the work. This draft DOES NOT represent final outcomes and will continue to evolve as discussions progress. While the front end of the process includes significant detail, the AESO is still assessing the most efficient study paths to enable ready-to-proceed BYOG large loads to advance quickly, without creating unnecessary timeline impacts for non-BYOG projects. Additional detail on study paths will be developed and shared in the coming weeks.
The posted draft process also includes comments where a future data centre regulation may affect certain process elements. In fall 2025, the Government of Alberta passed Bill 8, which enables the Minister to make regulations related to data centres. Given the interaction between the BYOG process and this potential regulation, the AESO will release a final process proposal once the regulation is published and the process has been updated accordingly.
Following release of the updated process proposal, the AESO will hold an industry-wide stakeholder session, with opportunities for questions and written feedback. The process will be finalized and implemented after stakeholder input has been considered. The AESO expects this engagement to occur in the second half of Q2 2026.
March 25, 2026
Following an update and planning session on Feb 9, the AESO held a “sprint week” with the working group Feb 18-20 (discussion only, no material provided). Meetings were held to review and discuss design and implementation questions related to process rollout needs, tethering agreements, project readiness requirements, study paths, and other topics. An additional meeting was held on March 3 for detailed discussions on project readiness requirements. The AESO will next provide the working group with a draft end-to-end process that incorporates the feedback from the meetings, and additional meetings will be held in April to further refine.
We will post another update and next steps in April, with broader industry engagement and rollout of the process occurring in the second half of Q2.
February 17, 2026
We held a kick-off session for the Phase 2A Large Load Working Group on Nov. 28. At their request, we also hosted a Q&A session with the AESO Chief Engineer on Dec. 10 to ensure common understanding of the methodology, inputs and assumptions underpinning the Phase I Interim Interconnection Limit (refer to slides 21-30 of the Phase I Large Load Integration Information Session presentation).
Between Dec. 4 and 17, we hosted one-on-one meetings with each LLWG-2A member to gather detailed input on connection process updates to accommodate large loads that (i) self-supply their own power on-site; (ii) enable net new generation on the transmission system; or (iii) require MW allocations. We provided a straw dog model outlining a sample connection process to support additional discussions. A 'What We Heard' summary has been prepared and provided to reflect common themes from the LLWG-2A individual meetings. Several design and implementation questions emerged, prompting an additional round of group meetings this month.
We'll provide another update and next steps in March.
November 26, 2025
The following organizations will participate in the Phase 2 Working Group, kicking off later this week.
- Beacon AI Centers
- Capital Power Corporation
- Dow Chemical Canada
- eStruxture
- Imperial Oil
- IREN Ltd
- KALiNA Distributed Power
- Kineticor Asset Management LP
- TransAlta Corp.
Thank you to everyone who applied to take part.
November 5, 2025
The AESO is launching the Large Load Working Group (“LLWG-2A”), a targeted industry engagement to explore and develop Phase 2A solutions for “bring your own generation” (BYOG) and MW allocations.
The LLWG-2A will collaborate with the AESO to develop a proposal to update the connection process, ensuring it recognizes and accommodates large loads that: (i) self-supply their own power on-site; (ii) enable net new generation on the transmission system; or (ii) require MW allocations. This effort aims to improve transparency and speed-to-market for projects that support Alberta’s reliability and competitiveness.
The LLWG-2A will follow a structured approach to develop the proposal:
- Identify key challenges in the current connection process
- Understand best practices and regulatory considerations
- Contribute to the design and validation of a proposal for BYOG and MW allocations
- Deliver a final proposal for broader industry consultation in 2026
To ensure informed and balanced input, we are targeting representation from the following groups:
- Data centre developers/end use customers (4 - 6 members)
- Generators (1 - 3 members)
- Industrial load customers (1 - 3 members)
LLWG-2A Selection
- Application Deadline: November 13, 2025
- Notification to Selected Members: November 20, 2025
Proposal Development
- Preliminary Kick-off Meeting (virtual): November 28, 2025
- 1:1 meetings with AESO: Week of December 1 and December 8
- Joint LLWG-2A meetings: as needed
Broader Industry Engagement
- Proposal Release, Engagement Sessions, and Written Comment Period: January-February 2026 (ETA)
For additional information, review the Phase 2A Working Group Supplemental Information and Terms of Reference. All interested stakeholders can apply to participate in the working group via the survey below.
April 21, 2026
The working group was provided with a draft of the front end of the process, including details on load applicability, generator qualification, application submission requirements, tethering agreements, and related terms and conditions. This draft reflected the working group’s discussions to date and was used as the basis for additional meetings held April 13–14 to further refine the approach. The AESO is now incorporating those updates into a revised process draft, which will be published shortly.
For transparency, the draft process shared with the working group is included with this update to provide visibility into the current direction of the work. This draft DOES NOT represent final outcomes and will continue to evolve as discussions progress. While the front end of the process includes significant detail, the AESO is still assessing the most efficient study paths to enable ready-to-proceed BYOG large loads to advance quickly, without creating unnecessary timeline impacts for non-BYOG projects. Additional detail on study paths will be developed and shared in the coming weeks.
The posted draft process also includes comments where a future data centre regulation may affect certain process elements. In fall 2025, the Government of Alberta passed Bill 8, which enables the Minister to make regulations related to data centres. Given the interaction between the BYOG process and this potential regulation, the AESO will release a final process proposal once the regulation is published and the process has been updated accordingly.
Following release of the updated process proposal, the AESO will hold an industry-wide stakeholder session, with opportunities for questions and written feedback. The process will be finalized and implemented after stakeholder input has been considered. The AESO expects this engagement to occur in the second half of Q2 2026.
March 25, 2026
Following an update and planning session on Feb 9, the AESO held a “sprint week” with the working group Feb 18-20 (discussion only, no material provided). Meetings were held to review and discuss design and implementation questions related to process rollout needs, tethering agreements, project readiness requirements, study paths, and other topics. An additional meeting was held on March 3 for detailed discussions on project readiness requirements. The AESO will next provide the working group with a draft end-to-end process that incorporates the feedback from the meetings, and additional meetings will be held in April to further refine.
We will post another update and next steps in April, with broader industry engagement and rollout of the process occurring in the second half of Q2.
February 17, 2026
We held a kick-off session for the Phase 2A Large Load Working Group on Nov. 28. At their request, we also hosted a Q&A session with the AESO Chief Engineer on Dec. 10 to ensure common understanding of the methodology, inputs and assumptions underpinning the Phase I Interim Interconnection Limit (refer to slides 21-30 of the Phase I Large Load Integration Information Session presentation).
Between Dec. 4 and 17, we hosted one-on-one meetings with each LLWG-2A member to gather detailed input on connection process updates to accommodate large loads that (i) self-supply their own power on-site; (ii) enable net new generation on the transmission system; or (iii) require MW allocations. We provided a straw dog model outlining a sample connection process to support additional discussions. A 'What We Heard' summary has been prepared and provided to reflect common themes from the LLWG-2A individual meetings. Several design and implementation questions emerged, prompting an additional round of group meetings this month.
We'll provide another update and next steps in March.
November 26, 2025
The following organizations will participate in the Phase 2 Working Group, kicking off later this week.
- Beacon AI Centers
- Capital Power Corporation
- Dow Chemical Canada
- eStruxture
- Imperial Oil
- IREN Ltd
- KALiNA Distributed Power
- Kineticor Asset Management LP
- TransAlta Corp.
Thank you to everyone who applied to take part.
November 5, 2025
The AESO is launching the Large Load Working Group (“LLWG-2A”), a targeted industry engagement to explore and develop Phase 2A solutions for “bring your own generation” (BYOG) and MW allocations.
The LLWG-2A will collaborate with the AESO to develop a proposal to update the connection process, ensuring it recognizes and accommodates large loads that: (i) self-supply their own power on-site; (ii) enable net new generation on the transmission system; or (ii) require MW allocations. This effort aims to improve transparency and speed-to-market for projects that support Alberta’s reliability and competitiveness.
The LLWG-2A will follow a structured approach to develop the proposal:
- Identify key challenges in the current connection process
- Understand best practices and regulatory considerations
- Contribute to the design and validation of a proposal for BYOG and MW allocations
- Deliver a final proposal for broader industry consultation in 2026
To ensure informed and balanced input, we are targeting representation from the following groups:
- Data centre developers/end use customers (4 - 6 members)
- Generators (1 - 3 members)
- Industrial load customers (1 - 3 members)
LLWG-2A Selection
- Application Deadline: November 13, 2025
- Notification to Selected Members: November 20, 2025
Proposal Development
- Preliminary Kick-off Meeting (virtual): November 28, 2025
- 1:1 meetings with AESO: Week of December 1 and December 8
- Joint LLWG-2A meetings: as needed
Broader Industry Engagement
- Proposal Release, Engagement Sessions, and Written Comment Period: January-February 2026 (ETA)
For additional information, review the Phase 2A Working Group Supplemental Information and Terms of Reference. All interested stakeholders can apply to participate in the working group via the survey below.
Signup Banner
Level of Engagement
Inform: Share information with stakeholders.
Lifecycle
-
Sept. 26 - Oct. 15, 2025 | Pre-Engagement Survey
Phase 2A: Large Load Integration | BYOG Process has finished this stage- Data Centre Update
-
October 2025 | Consideration of Pre-Engagement Survey Responses
Phase 2A: Large Load Integration | BYOG Process has finished this stage -
November 2025 - Present | Large Load Working Group 2A Engagement
Phase 2A: Large Load Integration | BYOG Process has finished this stage- Nov. 28, 2025 – LLWG-2A Kickoff
- Dec. 10, 2025 – Q&A Session on Phase 1 Limit
- Dec. 4 - 17, 2025 – AESO & LLWG-2A Individual Meetings
- Feb. 9, 2026 - LLWG-2A Update and Planning Session
- Feb.17 - 19, 2026 – LLWG-2A Sessions
- March 3, 2026 - LLWG-2A Session on Readiness Requirements
- April 13 - 14, 2026 - LLWG-2A Sessions
-
Q2 2026 | Phase 2A Industry Engagement
Phase 2A: Large Load Integration | BYOG Process is currently at this stage
Who's Listening
-
Program Manager, Large Load Connections
-
Sr. Stakeholder Engagement Advisor
Materials
-
Consolidated Stakeholder Feedback - July 13 2026 (posted 15July2026) (5.78 MB) (pdf)
-
Working Group Feedback July 2026 (posted 6Jul2026) (267 KB) (pdf)
-
Proposed BYOG Process (posted 26Jun2026) (997 KB) (pdf)
-
Large Load Integration Feedback Form - June 26 to July 13 2026 (posted 26Jun2026) (251 KB) (docx)
-
Large Load Integration Phase 2A BYOG Process Update (posted 18Jun2026 updated 24Jun2026) (4.83 MB) (pdf)
-
Large Load Working Group 2A
-
LLWG-2A BYOG Draft Front-End Process (posted 21Apr2026) (1.34 MB) (pdf)
-
LLWG-2A One-One Results and Next Steps (posted 25Mar2026) (711 KB) (pdf)
-
LLWG-2A Sprint 4 - Readiness Requirements (posted 25Mar2026) (627 KB) (pdf)
-
LLWG-2A Kick-Off Meeting - Nov. 28 2025 (posted 17Feb2026) (809 KB) (pdf)
-
LLWG-2A - What We Heard Summary (posted 17Feb2026) (894 KB) (pdf)
-
LLWG-2A AESO Straw Model for 1-1 Meetings (posted 17Feb2026) (124 KB) (pdf)
-
Phase 2A Working Group Supplemental Information (Posted November 5 2025) (958 KB) (pdf)
-
Phase 2A Working Group Terms of Reference (Posted November 5 2025) (228 KB) (pdf)
-
-
Data Centre Update (Posted 26Sep2025)
-
Data Centre Update (Posted 20Mar2025) (529 KB) (pdf)
Stakeholder Submissions
Related projects
Key Dates Archive
-
September 2025