Combined TRP & Amendments for the Connection Process | April 20 - May 1, 2026
We invite stakeholders to provide their feedback following the stakeholder sessions held on April 15 & 16, 2026 via the following stakeholder feedback form by end of day May 1. Thank you for your input.
To make it easier to provide input, we have combined feedback for both engagement workstreams into a single request. You only need to submit your feedback once. All feedback received will be reviewed and considered for both workstreams. You may refer to the stakeholder presentation to assist with your responses.
Instructions
- This feedback is open to all industry stakeholders.
- Please fill out the sections below as indicated.
- Only one completed feedback form will be accepted per organization.
- To upload your completed feedback form:
- You will need to be registered and signed in on the AESO Engage platform; and
- You will need to be on either the TRP & Supply SAS page, or the Amendments for the Connection Process page, which can be found on the AESO website at www.aeso.ca and follow the path: AESO Engage (found on very top navigation bar) > ISO Tariff Hub.; and
- Click on the "Submit your feedback here" box to upload your completed feedback form.
- All responses are due by May 1, 2026, and will be shared on AESO Engage in their original format. If you have any questions, please email stakeholder.relations@aeso.ca
Stakeholder Questions
Determining TRP Base Rate
Further to the April 15, 2026, discussion, we are seeking your input on how the AESO should engage with industry to develop an acceptable TRP Base Rate ($/MW). For example, preferences could include (bur are not limited to) discussion forums, facilitated workshops, confidential submissions, or a combination of approaches.
1. What engagement format would your organization prefer for this work, and why?
STS Contract Capacity
The AESO has proposed to apply the TRP rate to STS contracted levels. Following the October 2025 TRP session, the AESO requested feedback on what STS contract capacity should be based on, and what the consequences should be for going over STS. Further to the April 15, 2026, conversation, we want to hear your thoughts on those same questions, but for the perspectives of transmission connected suppliers; distribution connected suppliers; and sites that consume some of the produced energy on-site (for example, for on-site load processes, to charge energy storage, etc.)
2. What should STS contract capacity be based on?
3. What should the consequences be for going over STS contract capacity and what should that threshold be for going over (i.e. once in a year, 5% of time, over by a certain amount, etc.)
Proposed TRP Implementation
4. Do you have comments on the AESO’s proposed implementation of TRP? Please provide details.
Commitment Charge
5. Do you have comments on the commitment charge, including the conditions for refunds? Please provide details.
Transition Plan for In-Flight Projects
6. Do you have comments on the AESO's transition plan for in-flight projects? Please provide details.
Additional Feedback on the proposed Amendments for the Connection Process?
7. Do you have additional feedback specific to:
- Proposed TRP Implementation
- Commitment Charge; or
- Transition Plan for In-flight Projects?
Please provide details.