Fast Frequency Response ISO Rule Amendments
Consultation has concluded
Application Approved by Commission
In Decision 28937-D01-2024, dated May 24, 2024, the AUC approved the AESO's application, pursuant to Section 20.21(1)(a) of the Electric Utilities Act. The new and amended ISO rules and definitions came into effect on May 31, 2024.
Key Dates and Materials
March 22, 2024 | Response Letter and Stakeholder Comments and AESO Response Matrix posted (additional materials can be found in the AESO Materials section)
Purpose
In addition to proposing to create a new rule, Section 205.9, Dispatches for Concurrent Services, the AESO has identified necessary amendments to the following ISO rules and Consolidated Authoritative Document Glossary (CADG) Definitions:
- Consolidated Authoritative Document Glossary (CADG) Definitions (including a change to the Future Effective CADG-Defined Terms)
- Section 201.7, Dispatches
- Section 203.4, Delivery Requirements for Energy
- Section 205.2, Issuing Dispatches and Directives for Operating Reserves
- Section 205.5, Spinning Reserve Technical Requirements and Performance Standards
- Section 205.6, Supplemental Reserve Technical Requirements and Performance Standards
- Section 303.1, Fast Frequency Response Service
- Section 503.16, SCADA Technical and Operating Requirements
The AESO proposes to consult with Stakeholders on the Fast Frequency Response (FFR) ISO Rule Amendments which are the minimal rule changes necessary to articulate how discrete, technology-agnostic FFR will be used to support the AIES.