Section 503.6 and Section 503.18 Amendments
Important Dates & Materials
December 17, 2025 | Stakeholder Feedback due
November 26, 2025 | Letter of Notice and related materials posted
- Clean copy of Section 503.6, Frequency & Speed Governing
- Blackline of Section 503.6, Frequency & Speed Governing
- Clean copy of Section 503.18, Operation and Maintenance of Facilities
- Blackline of Section 50.18, Operation and Maintenance of Facilities
Background and Purpose
Section 503.6
On July 31, 2025, the AESO received an ISO Rule Proposal from TransAlta to amend Section 503.6, proposing to amend subsection 6 which has an incorrect reference. TransAlta identified that subsection 6 incorrectly references Section 503.19 and has proposed that the subsection should be corrected to reference Section 503.18, as follows:
6 The operator must, subject to Section 503.18 of the ISO rules, Operation and Maintenance of Facilities, operate the generating unit, aggregated facility, or energy storage resource with the governor system in service, in droop mode, and free to respond to frequency changes while:
(a) supplying active power to the interconnected electric system; or
(b) providing an ancillary service that requires a response to frequency changes.
The AESO has identified that the reference to Section 503.19 in subsection 6 is an error and agrees with TransAlta’s Rule Proposal that the reference should be corrected.
Section 503.18
On November 7, 2024, the AESO received an ISO Rule Proposal from Enfinite to amend Section 503.18, proposing to amend subsection 3(2) which has an errant omission. Enfinite identified that subsection 3(2) is missing subsection (b) and has proposed the following language be added, which carries over from the predecessor Section 502.6 Generating Unit Operating Requirements:
(2) The legal owner must:
(a) submit the operating data requested by the ISO, if available, no later than 5 business days after receipt of the notices set out in subsection 3(1); or
(b) if the operating data requested by the ISO is not available, advise the ISO in writing no later than 5 business days after receipt of the notice set out in subsection 3(1).
The AESO intended to transition subsection 7(1)-7(2) of Section 502.6 to subsection 3(1)-3(2) during the development of Division 503, which is evidenced by the Table of Concordance for the Transition from Division 502 to Division 503 of the ISO rules. The AESO agrees with Enfinite’s Rule Proposal that subsection 3(2) should be amended to correct the omission.
The Rule Proposals can be found on the ISO Rule Proposal page on AESO.ca.
Pursuant to Alberta Utilities Commission Rule 017, Procedures and Process for Development of ISO Rules and Filing of ISO Rules with the Alberta Utilities Commission, the AESO is providing notice and seeking feedback from the Stakeholders on a proposed amendment to Section 503.18.