Historical Key Dates
October 2024
Historical Key Dates
- Nov. 20,2024 | Cluster 2 update (part of the Grid Reliability Info. Session)
- Sept. 16, 2024 | Cluster Process Reassessment Fee Waiver
- Sept. 6, 2024 | Comments Due Cluster 1 Stage 2 Stakeholder Survey
- Aug. 1, 2024 | July 31 Information Session video recording posted
- July 31, 2024 | Virtual Information Session, Stakeholder survey open
- July 24, 2024 | July 31 Information Session Presentation and agenda posted
- June 5, 2024 | Additional Flexibility for MPs
- Jan. 31, 2024 | Cluster Assessment Process Information Session
- Recording posted Feb. 1, 2024
- Agenda & Presentation posted Jan. 24, 2024
- Dec. 4, 2023 - Jan. 5, 2024 | Cluster Assessment Process Survey
- Oct. 4, 2024 | Session 6, Information Session
- Recording posted Oct. 10, 2023
- Agenda & Presentation posted Sept. 27, 2023
Aug 3, 2023 - Feb. 29, 2024 | AUC Renewables Pause
- July 20, 2023 | Session 5 - Information Session
- Recording posted July 24, 2023
- Agenda & Presentation posted July 13, 2023
- Mar. 28, 2023 | Session 4 - Implementation Update
- Recording posted Mar. 30, 2023
- Agenda & Presentation posted Mar. 21, 2023
Design Stage
- Dec. 9, 2022 - Jan. 6, 2023 | Connection Process Streamlining Survey
- Oct. 18 - Nov. 2, 2022 | Session 3 Feedback Period
- Oct. 18, 2022 | Session 3 - Design
- Agenda & Presentation posted Oct. 11, 2022
- Jun. 28, 2022 | Session 2 - World Cafe
- Session Summary posted Jul. 26, 2022
- Stakeholder Comments posted Jul. 26, 2022
- Agenda & Presentation posted Jun. 21, 2022
- May 19, 2022 | Session 1 - Kickoff
- Recording posted May 19, 2022
- Agenda & Presentation posted May 12, 2022